Removed the floor pans in the cabin interior, prepped and primed all the surfaces which will be permanently sealed beneath the cabin floor. It was a lot more work than it looks like!
|
Just checking out how big the airplane will be with tailcone attached
|
Some remaining tailcone assembly and more fuselage layout.
|
Started work on wing stall warning system and pitot tube mount.
|
Continued work on stall warning system and pitot tube. Prepared wing interior for additional priming. Also began trimming cabin top.
|
Fuselage Sound Insulation fitting
|
Fuselage insulation installation. Front floor panel riveting. Gear weldment installation. Backage door operning stiffener installation. Tailcone service bulletin completion. More priming.
|
|
Preliminary attach of tailcone for match drilling and pre-priming prep.
|
Further tailcone attachment work. Matchdrilling, countersinking and shims.
|
Final priming after match fitting tailcone to fuselage. Performed final assembly and began riveting.
|
Start of tailcone attach riveting. Completed majority of side skin riveting.
|
Majority of tailcone attach riveting completed.
|
Started match drilling baggage area floors and door reinforcements.
|
Secured rear seat floor noise insulation with adhesive, preliminary installation of rear floor panels, started assembly of baggage door.
|
|